Erection Services - Steel
-
Rockingham Memorial Hospital
Harrisonburg, VA
CSE erected approximately 2500 tons of steel.
It was a 2 crane operation with a total of
45 erectors. The project duration was approximately 8 months with an erection value
of $4,750,000.00.
-
Founders Federal Credit Union
Lancaster, South Carolina
6000 Manhours
590 Tons of Steel
-
UVA Bed Tower Expansion
Project Amount: $1.5M
Man Hours: 11,069
Tons of Steel: 844 Tons
The project is adding 72 private patient rooms
to the front of the hospital. The new steel
framing is being supported by the existing
hospital structure and was erected at night to minimize pedestrian exposure to construction hazards.
-

Project: Cement Plant Finish Mill Process
Tons of Steel: 10,000
Multiple Crane & Contractor Operation
Critical Schedule Demands
Installed all Finish Mill equipment:
• Dust Collectors
• Conveyors
• Coolers
• Fans
• Hydraulic Systems
• Assembled and Installed Filter Units
• Field Fabrication